[ARCHIVED] City of Hibbing Paving Project Updates

construction-site-2023 with lights and barricade

Updated 6/6/2023


2023 Hibbing Paving Project Details (PDF)


To: Residents 

From: Jesse Story, Hibbing City Engineer

Date: June 1, 2023

 Greetings,

The City of Hibbing awarded the 2023 Paving project to KGM Constructors. As part of the project this year, we will be rehabilitating 21st Street from 1st Avenue to 7th Avenue East. The project details are as follows:

New bituminous surface

  • Partial curbing and sidewalk replacement. 
  • We will be removing and replacing any broken curbing. 
  • We will be removing and replacing any sidewalk that is adjacent to the broken curbing (where there is no boulevard).
  • We will be installing new handicap ramps at all intersections.

 There may be times when you cannot access your driveways during construction. We ask that you please be patient.

 Construction is planned to start on May 15th and should be completed in June.  

June 1st & 2nd – Pave the frontage road by Holiday and the Ford Garage, hope to get the base course and wear course completed

                                Bituminous Milling on Southview Drive-

June 5th – 9th –Updates: Pave Southview Drive, Pave the frontage Road by IronRange Tire-Complete

                                  Pave 1st Avenue Frontage Road-Complete

                                  Begin Placing the class 5 base on Pintar Road-Complete

                                  End of Week begin concrete removal on 21st Street

June 12th Updates– Pave Pintar Road-Complete

                                Pave 6th Avenue West, Pave 7th Fillman Addition- Paving is complete, need to shoulder

                                Finish Paving 19th Avenue East- Complete up to 26th Street (HPU project stopped progress)

                                21st Street-Concrete removals will begin 06/13/23 and will continue during the week, new concrete placement will begins the week of 06/19/23  

June 19th – 23rd – Pave 21st Street

                               Place shouldering material

If you have any questions or concerns please call me at 218-969-0629.

 

Thank you.

Jesse M. Story, P.E.

Hibbing City Engineer/Director of Public Works

 