This year’s sanitary sewer lining project, sidewalk replacement project and the street paving program each received a green light from city leaders earlier this month.
Sanitary Sewer Lining: the 2025 Sanitary Sewer Lining Project was awarded to low-bidder Insituform in the amount of $1,363,210. This bid came in under the amount budgeted for the year.
The City has been lining its sanitary sewers to reduce inflow/infiltration and to reduce the amount of sanitary sewer failures and to extend the life of the treatment plant. Including this project, the City has rehabilitated 140,939 of sanitary sewer main since 2013.
Sidewalk Replacement: the 2025 City Sidewalk Project was awarded to Bougalis Construction in the amount of $79,956.
Five residential petitions were received for sidewalk rehabilitation. The City will also be replacing sidewalks along 24th Street and 9th Avenue East as part of the Safe Routes to School portion of the project.
The project breakdown is $63,088 for the city portion and $8,169 for the residential portion. The department budgeted $75,000 for the project.
Street Paving: the 2025 City of Hibbing Paving Project was awarded to Mesabi Bituminous in the amount of $1,282,691. The budget breakdown is as follows: 2025 Minnesota State Aid Maintenance Funds of $454,102, plus the 2025 City Budgeted Amount of $1,030,743 for a total 2025 City Paving Budget of $1,484,845.
The following streets are on this year’s list:
- Michigan Street from 7th Avenue East to 12th Avenue East
- 11th Avenue East from Wisconsin Steet to Michigan Street
- 9th Avenue East from Michigan Street to Minnesota Street
- 12th Avenue East from Michigan Street North to alley
- Merryview Lane from 16th Avenue East to Gray Drive
- Gary Drive from Highway 169 to 16th Avenue East
- Diane Lane from Gray Drive going south
- 16th Street from 13th Avenue East to 16th Avenue East
- 4th Avenue East from 19th Street to Howard Street
- 16th Avenue East from 11th Street to 13th Street
- 12th Street from 12th Avenue East to 17th Avenue East
- 11th Street from 12th Avenue East to 16th Avenue East
- 12th Avenue East from 11th Street to 13th Street
- 13th Avenue East from 11th Street to 13th Street
- 14th Avenue East from 11th Street to 13th Street
- 15th Avenue East from 11th Street to 13th Street
- 2nd Avenue East from 21st Street to 19th Street
- Old Highway 169 from Rainey Road to Highway 169
- Elynwood Road from Old Highway 169 going south
LEETONIA
- Harold Avenue from 1st Street to 5th Street
- Dale Avenue from 3rd Street to 5th Street
- 1st Street from Morton Avenue to Harold Avenue
- 2nd Street from Morton Avenue to Harold Avenue
- 3rd Street from Morton Avenue to Harold Avenue
- 4th Street from north alley to south of Dale Avenue
To learn more or if questions, contact our Engineering Department at 218-312-1571.